Kitchen Renovation Cost in Different Cities in Canada

March 14, 2021 | Updated on: April 01, 2024

kitchen renovation cost Canada

Whether you're considering renovating Your Kitchen Space in Toronto, Vancouver, Montreal or Another Urban Center, understanding the financial aspects of a project is key to success. Kitchen renovation expenses depend on various factors  specific to each household and city - material costs and labor rates to permit fees and contractor availability. At Cut2Size we will provide an in-depth kitchen renovation costs analysis in order to help anticipate and plan for financial investments required. Whether you're aiming for a budget-friendly makeover or a luxurious overhaul, this post will guide you through valuable insights and practical tips tailored to the specificities of kitchen renovations in your exact province.

How to Plan a Kitchen Renovation?

Any room in the house, especially the kitchen, requires an individual approach and careful renovation planning. It is How to Plan a Kitchen Renovation incredibly unreasonable to rush planning a kitchen renovation because it is unpleasant to redo already completed work. Before proceeding with the kitchen’s renovation, you should first make a floor plan of the room with the kitchen’s dimensions and decide how to. 

It is essential to take the correct measurements of the space. Make sure that you have a laser to measure long walls to avoid mismeasurements. If the room is rectangular, measure the length and then the width of the room. Measure the height of the walls. Draw a plan on paper; mark the existing walls first. Measure and indicate the location of windows and doors. Once the room’s perimeter is mapped, it is necessary to show the old plumbing pipes, electrical outlets, gas lines, and heat registers. 

Think about the advantages and disadvantages of your existing kitchen. Is it functional? Is there enough storage space? Think about where you want your appliances and sink. Make a floorplan of your kitchen cabinets and indicate the fridge, sink, dishwasher, stove and oven, and microwave location. The kitchen plan should be well thought through because you will need to plan for electrical and plumbing work. 

Kitchen-Form

Making a Kitchen Design

Many people skip this stage, believing that they can keep all the details in their heads. This is a crucial step that, first Making a Kitchen Design ly, is going to help you to estimate your project. Second, you will have a better understanding of the amount of work that has to be done. Third, having a kitchen design will help you to avoid mistakes during your kitchen renovation. 

If you are not sure that it will be easy to create a design on your own, it is better to use a professional kitchen designer’s help. A professional kitchen designer will help you design an awesome kitchen. The kitchen design should take into account the location of cabinets, electrical, plumbing, and appliances. Condo kitchen design or townhouse kitchen design should maximize the storage and efficiency of the small space. There are tons of ideas for fantastic kitchens for small spaces available on Pinterest. 

After you have a kitchen design, you can start pricing the cost of the whole renovation. 

The kitchen renovation includes the following work:

  • Demolishing work;
  • New electrical wiring; 
  • New plumbing work;
  • Taping and sanding the walls; 
  • Painting the ceiling and walls;
  • Tiling work; 
  • Installation of the kitchen floor replacement or installation of a door;
  • Installation of baseboards;
  • Installation of switches, plugs, and light fixtures;
  • Installation of an air duct and hood;
  • Cold and hot water supply;
  • Countertops;
  • Cabinet installation;
  • Appliances installation.

When the kitchen design is ready, it becomes necessary to select a contractor and determine the project’s future costs. Prices for renovations offered by different companies or contractors may vary significantly. Therefore, getting a few quotes from various trades and suppliers is always a good idea. 

It is impossible to determine the level of prices for renovations, focusing solely on the price list. Most of the contractors give a fee based on the average kitchen size

The purpose of every estimate is to attract attention. Only a detailed estimate for the renovation provided after the site visit, measurements, and understanding of the work scope will include reliable information about the upcoming costs. Every kitchen renovation will cost differently; there are no two identical renovations. 

However, since the budgeting methods can vary significantly, is the company providing you with the quote analyzing all the necessary details? Or is it just the estimate of the total amount without going into details? When comparing estimates made by different companies, you should know that contractors use different methods to create an assessment to get a job.  Making a Kitchen

  1. 1. To have an attractive total amount, not all work necessary for the project may be reflected in the estimate. Such an estimate looks more appealing. However, in carrying out the reno, the unaccounted work will be presented for payment as "additional.” As a result, the actual cost of the project will significantly exceed the estimated one. A seemingly cheap renovation will become expensive. 
  2. 2. The cost of a renovation depends on the level of its complexity. For example, 10 x 10 kitchen cabinets can cost differently depending on the type of materials, hardware, and how many boxes and drawers are in them. Therefore, if the contractor provides you with a kitchen cabinets quote with no details, it might result in “additional costs.” Also, the cost depends on the size of the space. For example, condo renovation costs would be different from house renovation costs. 

If the contractor verified all the details and included them in calculating the work’s adequate cost, his price will be higher. The contractor’s estimate who did not go into more information and only applied the "base" rate will look more attractive at the very beginning. However, the difference in cost will certainly be presented for payment in the form of payment for "additional" or “extra” work.

Therefore, if you want to get a realistic renovation budget, take time to analyze and discuss the estimate’s details. The more detailed the quote you will get, the more money you will save in the renovation process. There will be no or minimal additional cost. Also, make sure you compare apples to apples. The most expensive quote is not necessarily for the reason that someone wants to rip you off. It most likely has lots of details that will help you avoid extra charges for work never included in the estimate. 

A low-budget kitchen renovation is only possible if you are handy enough to do it on your own. 

 

How Long Does a Kitchen Renovation Take?

A kitchen is an important place in a house and is often combined with the living room. It is not only for meal How Long Does a Kitchen Renovation Take preparation but also a gathering place, where families spend warm evenings together. That is why the renovation of a house often begins with the kitchen. What kind of work has to be done? Where to start? How long does it take to renovate? Let's take a look. 

The best condition for renovation is when a room is empty. Ideally, the homeowners are moving out of the house while the renovation is in the process; in this case, the chances of meeting the desired deadline are much higher. Otherwise, multiply the allotted time by two.

It is essential to start a renovation if you already have a kitchen design project in your hands. Otherwise, the renovation may take much longer, alterations and modifications and difficulties are not excluded. There are so many kitchen hardware options compared to the 60's kitchen or 70's kitchen. There is an opportunity to make your kitchen not only beautiful but also practical. 

A whole house kitchen renovation is not a five-minute job. It is a long process that requires a specific order of work and a certain amount of time. Below we list the main steps you will go through when renovating your kitchen. 

Stage 1 - Demolishing: 2-3 days

Demolishing

This requires the removal of old plumbing, cabinets, appliances, floors, and old doors. When the dismantling is over, clear the space of construction debris and start replacing the wiring. 

Stage 2 - Wiring: 3-5 days 

Wiring

First, you need to draw a diagram of your future electrical on the walls and ceiling.

Then mark out the plugs and switches. Ensure you do wiring according to the building codes. If you are not confident about doing it, hire a licensed electrician to perform this job.

Stage 3 - Plumbing: 3-5 days 

Plumbing

Old communications need to be replaced. Mark the plumbing location on the floor. Make sure everything works and is according to the new kitchen plan. If you have never done it before, hire a plumber. You need to know the codes to pass the inspection after the plumbing work is done. 

Stage 4 - New Windows Installation: 1-2 days 

Windows Installation

Old windows need to be replaced at this stage. Choose a high-quality window. Hire a professional window installer. 

Stage 5 - Walls Repairs: 1-2 days 

Walls Repairs

If your walls need to be fixed, do it at this stage. Fix with mud and prepare them for priming.

Stage 6 - Window Casings and Baseboards: 1-2 days 

Window Casings and Baseboards

Window casings and baseboards have similar installation methods. You will need a nail gun and a mitre saw to perform the job. Make sure you don't leave significant gaps between the boards. After the trims are in place, fill the gaps and nail holes with the filler. Once dry, they should be sanded and prepared for spraying. 

Stage 7 - Cabinets Installation: 2-7 days 

Cabinets Installation

If you are installing cabinets yourself, please read our article on how to install kitchen cabinets. There are detailed instructions on how to do it. 

Stage 8 - Protection 

cabinets protection

Make sure you protect your cabinets and floor if you are keeping them. It is an important step. 

Stage 9 - Wall Painting, Baseboard and Casing Spraying: 2-5 days 

Wall Painting

Different types of products should be used for walls and baseboards. Prime the walls first. Do not skip this step. The primer will help make the wall colour come through even more. After the primer is applied, you can start applying the first coat of paint. Let it dry. Follow the instructions on the colour that you use. Apply the second coat. Let it dry. Use a brush to paint the baseboards and casings. If you would like them to be sprayed, hire a professional painter. 

Stage 10 - Countertops: 1 day and Tiling Work 2-3 days 

Countertop installation

A stone countertop is a hardened surface that is impossible to cut and polish without having special machinery. Therefore you would have to hire a professional installer to perform the job. 

Stage 11 - Flooring Installation: 2-3 days 

Flooring Installation

Depending on what type of flooring that you picked, the installation of it will be different. Additionally, different sets of tools are required for different floor types. Familiarize yourself with the installation. 

Stage 11 - Appliance Installation: 1 day 

Appliance Installation

Every kitchen has a fridge and freezer, dishwasher, microwave, oven or stove, and hood fan. Appliance installation seems easy, but is it as easy as it looks? Some of the appliances need not only electrical power but also a water supply. Make sure that you are confident in installing the devices; otherwise, contact a professional. 

Stage 12 - Final Cleaning: 1-2 days 

Final Cleaning

Post-construction clean-up requires window and door cleaning, vacuuming, floor and cabinet wiping, and dusting off the light fixtures. 

The complete kitchen reno is a highly complex process that requires the labour of many different professional trades. To make it smooth, you should start once you have finalized the plan. Also, make sure that you order them in advance if you want non-stock items in your kitchen. If you decide to go with expensive kitchen cabinets which are custom made, add 6-8 weeks for ordering them. 

 

Kitchen Renovation Cost in Canada Based on Average Kitchen Size ( 10' x 10' ) 

The kitchen renovation price depends on the scope of the work. Complete kitchen renovation cost would be different from a kitchen remodelling price. 

City/Region :

Low budget kitchen renovation cost

Average kitchen renovation cost

Luxury kitchen renovation cost

Kitchen renovation cost in Toronto

$ 25,000 and up

$ 35,000 and up 

$ 55,000 and up 

Kitchen renovation cost in Mississauga

$ 25,000 and up 

$ 35,000 and up

$ 55,000 and up

Kitchen renovation cost in Vancouver

$ 35,000 and up

$ 45,000 and up 

$ 65,000 and up 

Kitchen renovation cost in Montreal

$ 20,000 and up

$ 45,000 and up

$ 55,000 and up

Kitchen renovation cost in Ottawa

$ 25,000 and up 

$ 40,000 and up 

$ 55,000 and up 

Kitchen renovation cost in Edmonton

$ 20,000 and up 

$ 35,000 and up

$ 50,000 and up 

Kitchen renovation cost in Calgary

$ 20,000 and up

$ 35,000 and up 

$ 50,000 and up

Kitchen renovation cost in Hamilton 

$ 20,000 and up 

$ 35,000 and up

$ 50,000 and up 

FAQs

Article by:

Valentina Melnikova - Lead Designer at Cut2Size

valentina@cut2size.ca

Office 403.366.7411

Hi there! I’m a millwork designer and an owner of a kitchen cabinet manufacturing company. With a team of professionals, I work on designing and manufacturing high-end millwork. Combining professional designing and manufacturing skills is what allows us to develop and translate our plans into a reality through our uniqueness and exclusive ideas. Our employees are highly skilled and creative thinkers that also utilize their professionalism and experience to take millwork to the next level. I’m very familiar with the industry and I take on each project from the design to the final product. With that said, if you’re looking for design advice or technician help, you’re in the right place.